The following works have been implemented:
- Survey and design;
- 6 kV OHL re-route from 3 GI construction site;
- Construction of more than 1.8 km of 6 kV OHL;
- Construction of crossing across the motor way for heavy cargo by inserted cable with the total length of 100 m with a gasket seal in concrete.